MBS AG is upgrading

26. November 2018

For the new building of the hall with fully automatic parts warehouse, the easily expandable and malleable pile foundations were made last week.

A total of 684 running meters of piles were installed, each 9 m deep. The individual foundation piles are thermally activated in order to be able to use them as an energy source for the intended heat pump.

The next step is the piping of the piles, for this a sand-gravel mixture is introduced as a substructure.

We will keep you informed about the construction progress.